A Budget Baseline That Shows How Wrong It Has Been
Most budget baselines are last year plus a percentage, and nobody checks them. We asked for a 15-month revenue forecast by entity and got one that tested itself on months it hadn't seen, compared itself with same month last year, and said its own range was too narrow.
Ask where next year's budget baseline came from and the honest answer is usually: last year, plus a percentage. Somebody picked the percentage in a meeting.
It isn't a bad method. It's quick and everyone understands it. The trouble is that nobody checks it. Nobody goes back and asks how wrong "last year plus a bit" was the last three times.
What a forecast owes finance
A statistical forecast can look like the opposite problem: a line on a chart, from a method nobody in the room can explain. Finance is right to distrust that too.
A forecast earns a place in the budget when it answers three questions.
- How wrong has it been? On months it didn't see, not the months it was fitted to.
- Compared with what? If it can't beat "same month last year", you don't need it.
- How sure is it? And is the range it draws honest?
We wanted to see what it looks like when a forecast answers all three. So we ran one.
What we ran
A made-up company, Northwind, with three entities in three currencies. One file of actuals: 45 months for each entity, February 2023 to October 2026. And the FY28 plan workbook from the scenario planning playbook.
We started a project with both files and asked one thing:
Forecast monthly revenue for each entity for the next 15 months (November 2026 to January 2028) from the actuals history. Tell me how accurate the forecast is and what you compared it with.
Every number below came back from Querri and matches a separate check we ran on the saved code and the files. The full walkthrough is in the statistical forecast playbook.
One step, and it tested itself. Querri planned a single step and ran it in about 70 seconds. It tried four methods per entity. A trend plus a month-of-year pattern won for all three.
Then it reported the error on the held-out months. The measure is WAPE: average error as a share of actual revenue.
| Entity | Same month last year | Forecast |
|---|---|---|
| US (USD) | 11.7% | 2.6% |
| CA (CAD) | 11.3% | 5.5% |
| UK (GBP) | 10.9% | 3.9% |
| All three | 11.3% | 4.0% |
The other naive answer, repeating the last value, was off by 8.0%. So the forecast had 65% less error than same month last year. That's a record of past error, not a promise about next year.
Each entity stayed in its own currency and the three were never added together.
It said its own range was too narrow. The chart draws an 80% range around the forecast. Querri measured it: only 63% of the latest held-out months landed inside a range sized on the earlier windows. For CA and the UK it was 56%.
So it widened those two ranges and told us to treat them as optimistic. It added two more warnings. The test scored 9 months ahead and the forecast runs 15, so months 10 to 15 are less certain. And with about 3.75 years of history, each month's seasonal pattern rests on three or four observations.
All of that is on a Model report tab that comes with the step. So does a Download model button. It gives you the fitted model as a file you can load in Python.
It kept a feature only where it helped. We wondered whether working days mattered. We didn't add them. We asked Querri to test them:
Add the number of working days in each month as a feature and keep it only if it lowers the held-out error.
It ran as version 2 of the same step, with the same test. Working days lowered the error for CA, from 5.5% to 5.4%, so CA kept them. The UK came out the same either way. The US got worse, 2.8% against 2.6%, so they were dropped there. Overall: 4.0% both times.
Querri also said what the feature was: Monday to Friday counts, no public holidays. It suggested a holiday calendar as the next thing to try.
Then hold the plan against it
A baseline is for comparing. So we asked where the FY28 Base plan runs more than 5% above the forecast, by entity and month.
Querri pulled the Base revenue out of the plan workbook, matched all 36 entity-months to the forecast, and found one. The US in January 2028: 664,826.77 planned against 630,173.30 forecast, 5.5% above.
Everywhere else the plan is at or below the forecast. For the year:
| Entity | Base plan | Forecast | Plan vs forecast |
|---|---|---|---|
| US (USD) | 7,557,504 | 7,781,104 | -2.9% |
| CA (CAD) | 2,920,527 | 3,309,832 | -11.8% |
| UK (GBP) | 1,562,738 | 1,713,636 | -8.8% |
It also pointed out that the one breach is at the far end of the horizon, where the forecast is least certain, and said to treat it as a flag to review.
The more interesting finding is the other direction. CA's plan for the year is 11.8% under the forecast. That might be deliberate caution. It might be a plan nobody had compared with the history. Either way, it's a question you can now ask.
The same habit, on a different question
The same checks apply to driver analysis. In a separate run we gave Querri a price list of 1,532 rows and asked what drives list price.
Before fitting anything it audited the inputs. It left the SKU out, calling it "a key for the product, not a property of it". It held whole SKUs out together when it validated, because each one appears about five times. Its held-out error was 5.92 against 77.6 for guessing the average.
And it reported something easy to miss. Unit cost correlates 0.98 with price on its own, but adds almost nothing once category, brand and size are in the model.
What it's worth
- Find out how wrong last year's baseline was. If nobody knows, that's the finding.
- When someone hands you a forecast, ask the three questions: how wrong, compared with what, how sure.
- Look for where the plan and the trend disagree most. Those are the lines to talk about first.
How far this goes
This is one revenue line per entity and 45 months of history. The model knows trend and season, and working days where they helped. It doesn't know about a price change or a new product. That's what a baseline is for. It says what happens if the pattern holds, and the plan is where you say what's different.
Try it
The playbook has the actuals history, the plan workbook and every prompt. It takes about fifteen minutes, and then you can swap in your own history.
It sits alongside three other finance playbooks: live budget vs actual, group consolidation and driver-based scenario planning. Pricing is here.